Current Projects

Downtown Fate

The first phase of downtown Fate street reconstruction will begin the week of October 22, 2018 (weather permitting). This area is expected to be closed until April 2019.

The railroad crossing at WE Crawford Ave. will be replaced during this time frame.

TxDOT will also work on the intersection of WE Crawford Ave. and SH 66.

NO THRU TRUCKS - Truck are expected to follow detour signs. (additional map)

Downtown Detour

Truck Route

FM 551 at SH 66

UPDATE: The Dallas, Garland and Northeastern Railroad (DGNO) portion of the repair is complete including new signal and arms. 

TxDOT will close the intersection of FM 551 at SH 66 until the week of 10/31/18 to add turn lanes at FM 551 and SH 66, railroad re-planking, installation of new signals and arms at the crossing is now complete. The intersection improvements are expected to take 3 to 4 weeks weather permitting.

Downtown Detour

Ben Payne Road

Ben Payne Road (from Hwy 66 to LaFayette Dr) is complete with Asphalt overlay. The only remaining item is striping which has not yet been scheduled. This project was placed on hold during construction of Woodcreek Phase 8B but was given the approval by city Council to complete the road surfacing.

Blackland Road

Contract has been awarded to Texana Land & Asphalt
Notice to proceed has been issued
Estimated start date: May 14th, 2018

Blackland Road Asphalt Repair
There will be various small repairs to the existing asphalt roadway from I30 to Greenbriar Road. The repairs will not cause the roadway to be shut down. Residents should expect minor delays and follow flag men onsite. This work is now complete.

Blackland Road Concrete Panel Repairs
The existing concrete sections of Blackland Road from Northview to the Greenbriar intersection will be removed and replaced. This work is now complete.

Blackland Road Reconstruction

UPDATE: This project is currently ahead of schedule weather permitting the anticipated completion is November 2018.

Blackland Road from Greenbriar to approximately 700 feet north of Sun Valley Drive will be reconstructed from June 2018 to May 2019. Residents shall expect delays during this time frame. Two-way, one lane traffic is expected. Flaggers will be directing traffic during the day, while standard traffic control devices will be in place at night time. It is anticipated the top portion of the roadway (approximately 7”-8” of asphalt) will be removed. The existing subgrade/clay soils under the roadway will be treated to provide for a hard, compacted surface under the future roadway. Once the subgrade is complete, the asphalt will be placed on the surface. New pavement markings will be installed once the roadway is complete. In addition to the paving improvements, drainage improvements consisting of the removal and replacement of the driveway culverts along the roadway will occur. This will not disrupt the traffic along Blackland Road, however, the contractor will be coordinating with the residents living directly on Blackland Road regarding access to their homes.

Blackland Road Detour 2


Willowbrook Lane 

The asphalt millings from Blackland Road are being used to grade and level Willowbrook Lane starting July 2, 2018 until July 6, 2018. This work is now complete.

Railroad Crossings

Contract has been signed and submitted to DGNO Railroad, TRAK Time Railroad contractors of Fate was awarded the project. 

DGNO has received the materials in Dallas Texas.

Estimated start date: October 2018
Estimated end date: October / November 2018 

Signals

I-30 and FM 551 TxDOT Signal approved
Design complete
Estimated start date: August 27, 2018
Estimated complete date: October 31, 2018

Hwy 66 and CD Boren TxDOT Signal Warranted January 11, 2018
City Staff currently reviewing TxDOT's design -- will request the addition of sidewalks.
Estimated start date: No additional information from TxDOT at this time.

Railroad Crossings, Rochelle, Blackland, Greenbriar, North Ben Payne, Northview, Carrington and Downtown Fate. 

Fate City Council approved a $6.8-million-dollar investment on road repairs and construction during the Monday, December 4 2017 City Council meeting. Several projects included are the reconstruction of the railroad crossing at Riding Club Road, Ben Payne Road and at the Crawford/HWY 66 intersection.Rochelle Road will receive crack seal to maintain the previously improved road. Blackland road will have areas of replacement, asphalt reconstruction, crack seal as well as some drainage work. Greenbriar Road construction will include crack seal and surface repair. Sections of North Ben Payne Road are planned to be repaired prior to the four-lane concrete section planned in the next one to two years.  Finally, Northview and Carrington Drive construction includes portions of concrete panel replacement.

Also included is a redevelopment for the Fate Downtown area blocks (FM 551 to Brown and Brown Ave. to Barnes Ave.) to include roadwork and electric and sewer lines. Fate City Council has developed a plan to create quality vertical mixed use developments to make a walkable gathering place for residents to live, work and play that is also financially productive economic development.